PV Magazine•10-28-2025October 28, 2025•1 min
powerplantFrom ESS News
Earlier this year, Tennet’s large-scale introduction of time-dependent transmission rights (TDTR) contracts in the Netherlands offered a glimmer of hope to more than 70 GW of customers, mainly large-scale battery energy storage projects, currently stuck in the grid connection queue. According to the latest information, the lion’s share of the newly unlocked grid capacity will be allocated to batttery storage.
The Dutch transmission system operator said that up to 9.1 GW of capacity is available on the high-voltage grid during off-peak hours – capacity that could be effectively utilized through TDTRs.
TDTR give customers connected to the TenneT high-voltage grid the right to transport for a fixed number of hours per year, at least 85% of the time.
To continue reading, please visit our ESS News website.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
powerplant
Renewable Energy Magazine•May 1, 2026•3 min
powerplant
PV Magazine•May 1, 2026•3 min
powerplant
Offshore Wind Journal (Riviera)•May 1, 2026•2 min
powerplant
Canary Media•May 1, 2026•5 min
powerplant
Energy Global•May 1, 2026•3 min
powerplant
Energy Global•May 1, 2026•2 min
powerplant
Solar Quarter•May 1, 2026•2 min
powerplant
PV Magazine•Apr 30, 2026•2 min
powerplant
Offshore Wind Journal (Riviera)•Apr 30, 2026•1 min
powerplant
Energy Global•Apr 30, 2026•3 min
powerplant
Renewable Watch•Apr 30, 2026•2 min
powerplant
Powerline•Apr 30, 2026•1 min
powerplant
Renewable Energy Magazine•Apr 30, 2026•2 min
powerplant
Canary Media•Apr 30, 2026•3 min
powerplant
Energy Global•Apr 30, 2026•3 min
powerplant
Nuclear Engineering International•Apr 30, 2026•6 min
powerplant
Solar Quarter•Apr 30, 2026•2 min
powerplant
Power Technology•Apr 30, 2026•3 min
powerplant
Switchgear Magazine•Apr 29, 2026•2 min
powerplant
PV Magazine•Apr 29, 2026•2 min