##  **Basic Details**

| Item | Information ||——|————-|| **RfS No.** | SECI/C&P/IPP/11/0009/25-26 || **Dated** | 24 September 2025 || **Total Capacity** | 3,410 kW || **Mode** | RESCO (Capital expenditure by bidder; SECI/institute pays fixed tariff) || **Project Locations** | 11 projects across India |

##  **Project-wise Capacity & Location**

| Project | Institute | Location | Capacity (kW) ||———|———–|———-|—————-|| P-1 | IIEST | Shibpur, West Bengal | 490 || P-2 | NITTR | Kolkata, West Bengal | 260 || P-4 | IIM | Tiruchirappalli, Tamil Nadu | 700 || P-5 | SVPISTM | Coimbatore, Tamil Nadu | 100 || P-6 | Udaan Bhawan | New Delhi | 500 || P-7 | RGNAU | Amethi, Uttar Pradesh | 175 || P-8 | CIIL | Mysuru, Karnataka | 200 || P-9 | NIFT | Bhubaneswar, Odisha | 110 || P-10 | HNBGU (Chauras Campus) | Srinagar Garhwal, Uttarakhand | 640 || P-11 | HNBGU (Srinagar Campus) | Srinagar Garhwal, Uttarakhand | 235 || **Total** | | | **3,410 kW** |

> *(Note: P-3 not listed – possibly omitted or not awarded in this tranche)*

##  **L1 Winners (Rank 1) by Project**

| Project | L1 Bidder | Fixed Tariff (INR/kWh) ||———|———–|————————|| P-1 (IIEST) | Sunanda Solar Balaji Energy | 3.44 || P-2 (NITTR) | Sunanda Solar Balaji Energy | 3.51 || P-4 (IIM Trichy) | Sunanda Solar Balaji Energy | 3.15 || P-5 (SVPISTM) | Power Genesys | 3.95 || P-6 (Udaan Bhawan) | Sunanda Solar Balaji Energy | 3.26 || P-7 (RGNAU) | Sunanda Solar Balaji Energy | 3.80 || P-8 (CIIL) | Sunanda Solar Balaji Energy | 3.62 || P-9 (NIFT) | Sunanda Solar Balaji Energy | 3.80 || P-10 (HNBGU Chauras) | Sunanda Solar Balaji Energy | 3.71 || P-11 (HNBGU Srinagar) | Sunanda Solar Balaji Energy | 3.71 |

##  **Key Observations**

### 🥇 **Dominant Bidder****Sunanda Solar Balaji Energy Development Private Limited**– Won **9 out of 11 projects** as L1– Consistently offered the lowest tariffs (₹3.15–₹3.80/kWh)

### 🥈 **Other L1 Winners**– **Power Genesys Private Limited** – won P-5 (Coimbatore) at ₹3.95/kWh

### 📉 **Tariff Range (L1)**– **Lowest**: ₹3.15/kWh (IIM Trichy, 700 kW)– **Highest**: ₹3.95/kWh (SVPISTM Coimbatore, 100 kW)

### 📈 **Competition**– **Solaris Electrical Services** was consistently Rank 2 or 3 across most projects, with tariffs between ₹3.75–₹4.30/kWh– **Kshitij Kumar Choudhary** (individual bidder) appeared in top ranks across several projects